Repair work undeterred by explosion
Reference
to the newspaper
By Patrick Badgley
THE WASHINGTON TIMES
Friday, February 21, 2003
The 16.1-inch snowfall and
a manhole explosion in Georgetown this week won't delay the $40
million project to replace wiring underneath the streets in the
Northwest community, D.C. officials said yesterday.
Organizers of the infrastructure-refurbishment
project took into account matters such as inclement weather when
setting the completion date, said Karyn Good, the District's communications
director for the project.
"We're starting to chip
away at those dates, but the project is still on schedule,"
Ms. Good said, adding that workers have had to delay work 10 days
this year compared with three in 2002.
Construction is on schedule to end on M Street NW in spring 2004
and on Wisconsin Avenue NW a year later.
The upgrade of pipes and wires
was initiated by Potomac Electric Power Co., Washington Gas, the
Water and Sewer Authority and the D.C. government after a series
of manhole explosions, smoking sewers and power outages.
Wednesday's explosion occurred
almost three years after three underground blasts catapulted manhole
covers into the air, shaking Georgetown enough for dozens of businesses
to close for a day.
Portions of M Street and sidewalk
crumbled, and windows shattered. A couple of dozen businesses
and some residents between 31st Street and Wisconsin Avenue along
M Street lost power.
No utilities had to be turned off Wednesday.
Georgetown has some of the
city's oldest wiring. After investigating a June 2001 power outage,
Pepco discovered that its cables could overheat if wires became
too worn. Businesses said that outage caused losses of $8 million.
Tim Sargeant, corporate spokesman
for Washington Gas, said the company added new piping two weeks
ago 20 feet to 30 feet from where Wednesday's explosion occurred.
He said he couldn't speculate
on whether the construction was related to the break of a three-quarter-inch
pipe rising from a 6-inch gas line on M Street. Workers sealed
the gas leak Wednesday afternoon, and crews from Pepco checked
underground cables.
Firefighters and gas crews
checked nearby establishments for the presence of gas, evacuated
three buildings and drilled holes into the street to allow ventilation,
Mr. Sargeant said. One side of the two-way street was open by
9:30 p.m. Wednesday, and the street was open in both directions
at 2:20 a.m. yesterday.
The D.C. fire department is
responsible for finding out what ignited the natural gas. Alan
Etter, a fire department spokesman, yesterday said he knew of
no new developments in the investigation.
David Frandano, a manager
at J. Paul's restaurant nearby, said the explosion sounded like
a mix between a car wreck and a gunshot, and that the odor of
gas was strong. Mr. Frandano said a plume of smoke mixed with
snow filled the air surrounding the manhole.
The commotion cost the restaurant
thousands of dollars, he said. "It's become almost accepted
as something that can happen around here," said Mr. Frandano.
"But to think someone could be walking on it — it definitely
would kill or maim them — is scary." The construction near
the restaurant also is costing the restaurant business, he said.
|